Three phases of the Three Gorges Project
( 2003-07-01 17:31) (Chinadaily.com.cn)

Three Construction Phases

First phase, 1993-1997 (five years): Project preparation and first stage of construction, culminating in the damming of the Yangtze River in November 1997. The water of the Yangtze River was diverted through a man-made canal - the diversion channel, and the water level in the Three Gorges area rose by as much as 10 meters as a result.


Second phase, 1998-2003 (six years): The second stage culminates in the first batch of turbines beginning to generate hydropower and the permanent shiplock being put into operation. The reservoir is filled between June 1 and 15, 2003, when the water level in the Three Gorges have risen from the previous 66 meters above sea level to the current 135 meters.

TGP-Second Phase


Third phase
, 2004-2009 (six years): The project is to be completed in 2009, when all 26 generators will be operating. The water level will be raised to 156 meters in September 2006. At the completion of the project in 2009, the water level will reach 175 meters, referred to as the "normal pool level.
TGP Third Phase




   
Close  
  Go to Another Section  
     
 
 
     
  Article Tools  
     
  E-Mail This Article
Print Friendly Format
 
     
   
        .contact us |.about us
  Copyright By chinadaily.com.cn. All rights reserved  
饶平县| 平果县| 离岛区| 抚宁县| 信阳市| 方山县| 邵东县| 茶陵县| 大余县| 疏勒县| 湖南省| 容城县| 嵊泗县| 社旗县| 黄陵县| 达拉特旗| 四川省| 莆田市| 德兴市| 商丘市| 阿拉善右旗| 高陵县| 嵊泗县| 若羌县| 岢岚县| 敦煌市| 宿迁市| 高安市| 南投市| 永顺县| 新干县| 舞阳县| 虞城县| 香河县| 辽宁省| 景德镇市| 梁平县| 吕梁市| 文山县| 肃宁县| 鄂托克旗|